Those applying for a new electricity connection in NOIDA need to visit the following office:
Paschimimandal Vidyut Vitran Nigam Ltd.,
1st Floor, Above PNB Bank,
Atta Market, Sector 18
NOIDA - 201301
Location: Just outside the Sector 18 Metro Station exit, along the line of shops on the right side.
Timings: 10:00 AM to 2:20 PM
Documents Required:
- Application form (blue color) - can be collected at PVVNL office counter no. 1-4
- (a) For Original Allottee: Allotment Letter, Possession Letter, Lease Deed Copy, (b) For Subsequent Owners: Transfer Memorandum, Transfer Deed cum Sale Deed (copy both sides)
- Fitment Report: To be collected from one of the three designated "A Class Electricians" registered with NOIDA authority. Names & contacts are displayed on the PVVNL notice board. The nearest one is "Singhal Electricals", opposite Nathu Sweets.
- Identity Proof
Procedure:
- Fill up the application form, attach photograph and get it attested by a Class-I Gazetted Officer or by your bank
- Sign on all pages of the photocopied documents
- Attach the above docs to the application and get them confirmed by at one of the counters (1-4). Collect acknowledgment slip and go to payment counter
- Make payment at Cash Counter right outside the PVVNL office
- Installation of the meter depends on availability. It is currently available within two weeks.
- The cost of a 7Kw connection is Rs.12,475. The minimum needed is a 5Kw connection.
- The "cost" of a "Fitment Report" varies according to your bargaining skills. The current asking price seems to be Rs.500-Rs.600
4 comments:
Hi
>>The cost of a 7Kw connection is Rs.12,475. The minimum needed is a 5Kw connection.
Do you know which all papers are needed to change the load from 7KW to 5KW ? What will be the changes in fixed charges ? 7KW is 455/month so how about for 5KW or 4KW etc >
can u pls let me know what all can be run with 5KW of connection?
I want to take a new connection for 2BHK flat,how much will be the sufficient to run all electrc appliances with 2 ACs as well.
And after how much time will we get the connection?
Is there any black money required to be given to office?
Hi Shobjit:
A standard one-tonne AC consumes 1.335kW/hour. So a 5KW connection would easily run two ACs. Since you are likely to use other high-Wattage equipment (toaster,iron,microwave) simultaneously, it might be better to go for a 7KW connection.
Time taken for connection: 2-3 weeks.
Black-money: I found the PVVNL officers very professional. Nobody asked for a bribe. The line-men who come to install the meters & cables are, of course, a different story! :(
Nice blog. Thanks for sharing such an useful information.
Taxi Service in Lucknow | Cab Service in Lucknow
Post a Comment