Procedures: Getting A New Electricity Connection


Those applying for a new electricity connection in NOIDA need to visit the following office:

Paschimimandal Vidyut Vitran Nigam Ltd.,
1st Floor, Above PNB Bank,
Atta Market, Sector 18
NOIDA - 201301

Location: Just outside the Sector 18 Metro Station exit, along the line of shops on the right side.
Timings: 10:00 AM to 2:20 PM

Documents Required:
  1. Application form (blue color) - can be collected at PVVNL office counter no. 1-4
  2. (a) For Original Allottee: Allotment Letter, Possession Letter, Lease Deed Copy, (b) For Subsequent Owners: Transfer Memorandum, Transfer Deed cum Sale Deed (copy both sides)
  3. Fitment Report: To be collected from one of the three designated "A Class Electricians" registered with NOIDA authority. Names & contacts are displayed on the PVVNL notice board. The nearest one is "Singhal Electricals", opposite Nathu Sweets.
  4. Identity Proof
Note: An affidavit is no longer required along with the application


Procedure:
  • Fill up the application form, attach photograph and get it attested by a Class-I Gazetted Officer or by your bank
  • Sign on all pages of the photocopied documents
  • Attach the above docs to the application and get them confirmed by at one of the counters (1-4). Collect acknowledgment slip and go to payment counter
  • Make payment at Cash Counter right outside the PVVNL office
  • Installation of the meter depends on availability. It is currently available within two weeks.
Cost:
  • The cost of a 7Kw connection is Rs.12,475. The minimum needed is a 5Kw connection.
  • The "cost" of a "Fitment Report" varies according to your bargaining skills. The current asking price seems to be Rs.500-Rs.600






4 comments:

Amit Gupta said...

Hi

>>The cost of a 7Kw connection is Rs.12,475. The minimum needed is a 5Kw connection.

Do you know which all papers are needed to change the load from 7KW to 5KW ? What will be the changes in fixed charges ? 7KW is 455/month so how about for 5KW or 4KW etc >

Unknown said...

can u pls let me know what all can be run with 5KW of connection?
I want to take a new connection for 2BHK flat,how much will be the sufficient to run all electrc appliances with 2 ACs as well.
And after how much time will we get the connection?
Is there any black money required to be given to office?

Dinakarr said...

Hi Shobjit:
A standard one-tonne AC consumes 1.335kW/hour. So a 5KW connection would easily run two ACs. Since you are likely to use other high-Wattage equipment (toaster,iron,microwave) simultaneously, it might be better to go for a 7KW connection.

Time taken for connection: 2-3 weeks.
Black-money: I found the PVVNL officers very professional. Nobody asked for a bribe. The line-men who come to install the meters & cables are, of course, a different story! :(